14) A contractor estimated that her expenses for a construction project would be between $700,000 and $750,000 She has already spent $496.000 How much more can she spend and remain within her
estimate?
Write as an inequality!

Answers

ansver
Answer from: makaileep7449

204000 < x < 254000

Step-by-step explanation:

700000 < 496000 + x < 750000

Solve for x by subtracting 496000 from both sides

204000 < x < 254000 > so we can conclude that she can spend between $204,000 and $254,000 more and remain within her estimate.

ansver
Answer from: Quest

(d)

step-by-step explanation:

given: the line in the graph passes through points (5,30) and (6,26).

then, the equation of line is:

y-y_{1}=\frac{y_{2}-y_{1}}{x_{2}-x_{1}}(x-x_{1})

y-30=\frac{26-30}{6-5}(x-5)

y-30=-4(x-5)

y-30=-4x+20

y=-4x+50

now, put y=a(n) and x=n,

a(n)=-4n+50

a(n)=-4n+46+4

a(n)=46-(n-1){\times}4

hence, option d is correct.

Ascientist cools some water at a constant rate. the graph and table show how the temperature of the
ansver
Answer from: Quest

dc=6 square root of 3 and ac is 12 square root 3

c and d

step-by-step explanation:

square root of 3/2 = 18/c

cross multiply to get 18*2=√3*c

36/√3 * √3/√3 = c

c= 36*√3/3

c=12√3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:30, hihihi129473838
For what is the measure of the angle at the top of the shed? a. multiplication of areas b. squaring of areas c. addition of areas d. division of areas
Answers: 1
image
Mathematics, 21.06.2019 20:00, stichgotrich7159
Michael is training for a marathon. in his first week he plans to run 8miles. what path should he take
Answers: 1
image
Mathematics, 21.06.2019 21:30, lraesingleton
Acompany charges $0.10 for each letter engraved. bobby plans to spend no more than $5.00 on the engraving on a jewelry box. write and solve an inequality to find the maximum number of letters he can have engraved.
Answers: 1
image
Mathematics, 21.06.2019 22:20, stalley1521
Which of the following is missing in the explicit formula for the compound interest geometric sequence below?
Answers: 1
You know the right answer?
14) A contractor estimated that her expenses for a construction project would be between $700,000 an...